Maintaining and improving the Gurdwara is an ongoing Seva. Below is a transparent view of our active and planned capital projects, funded entirely by the Sangat's daswandh.
Active
0
Planning
4
Completed
2
Total
6
NO.PROJECTSTATUSBUDGETTARGETPROGRESS
01 · COMPLETE£75000
Main Building Lift Replacement
Replacing the main building passenger lift to improve accessibility for elderly sangat and wheelchair users. Actual spent £82380
Dec 2025
since Aug 2025
100%
02 · PLANNING£42,000
Kitchen HVAC Air Flow
Upgrading the langar kitchen ventilation system to improve air quality and energy efficiency for sevadars.
Oct 2026
since Mar 2026
25%
03 · PLANNING£95,000
New Building Boiler Replacement
Replacing aging boilers in the new building with high-efficiency condensing units, reducing heating costs and emissions.
Dec 2026
since Sept 2026
10%
04 · COMPLETE£300,000
Kitchen Refurbishment
Aged Main Kitchen refurbishment
Mar 2026
since Feb 2026
95%
05 · PLANNING£50000
External Lighting & CP
Major external lighting refresh including the courtyard, parking, and Nishan Sahib floodlighting.
Dec 2026
since Aug 2026
5%
06 · PLANNING£20m
Hanworth Road Site
Acquisition and development planning for adjoining land — community use under consultation with the sangat.
Dec 2027
since Jun 2026
5%
· Help us build ·
Daswandh sustains every brick.
These projects are funded by the Sangat. A targeted donation can be made to a specific project; please contact the office to arrange.